Management of the industrial master plan using Agile principles - Mews Partners
01

Problematic

The master plan is split in a dozen programs that aim to increase the agility of the Supply Chain to facilitate the launch of new offers and services, adapt the network to changing volumes, exploit and value data (particularly tracking), better operate with the group’s subsidiaries, improve service quality and optimize costs.

The management of this assignment, from the clear definition of the objectives to the operational management of interactions, is a key issue to be addressed.

02

“There is no favorable wind for the sailor who doesn’t know where to go”

Letters to Lucilius, LXXI, Seneca

Process

The first step was to understand the context of the project by conducting interviews, going on the field and working on the key objectives of each program to determine their scope of autonomy and interaction.

The second step was to set up a management system for decisions and actions in the backlog (as well as its sequencing, PIP SAFe) using visual management.

The third step focused on pull scheduling management of the interactions between sub-programs, the master plan and external projects.

Finally, the last step’s aim was to transfer the new operating modes by organizing the relays, training the Scrum masters and formalizing the repository within a booklet that mixed Lean and Agile practices.

12

Voices of customer and Obeyas defined

150

150 major interactions controlled

1

"Big Book Agile"

1

Agile self-diagnosis tool

Result

03

Result

After one year of support, the new steering organization is up and running. A convergence committee and a coordination committee have been set up. All sub-programs have built their Agile visual management system as well as 2 sites in the regions. They can be evaluated using a specifically defined agile maturity self-diagnosis tool.

Coordination with the program managing IS evolutions is operational.

Arbitration and acceleration seminars have been organized to deal with difficult cases.

Packaged training courses were delivered and conducted for about thirty employees and all the methods used were formalized in a reference book that was widely distributed. Training sessions are systematically provided for newcomers to the project platform.

Discover our stories

Support in the deployment of IS for a naval actor

Large naval projects are characteristic of industrial complexity: multidisciplinary, involving a multitude of stakeholders and constraints, with long development time cycles that are sometimes out of phase with those of technologies. System engineering appears to be an essential tool to master this complexity.

Find out more

Visual management in project mode in the aeronautics sector

Visual management at the service of projects, or how to both improve efficiency and create a new dynamic in project teams.

Find out more

Are you interested in these topics?

Join the tribe

Follow us on social media